Water consumption doubles in the summer
From the viewpoint of the Alavus water utility, the growth of the Kyläkauppa area in Tuuri has meant repeated measuring reviews on their water supply network. The water comes from two intake facilities, which are located about 10 and 15 kilometres from the village. If one line would fail, the other line could supply enough water – provided, that they were lucky enough. If such failure took place in the middle of the summer, a shortage of water would be a very likely scenario.
“Summer brings big crowds to the area, and the water consumption can be as high as 300 cubic metres per day. On the other hand, 130 cubic metres per day is more than enough in winter”, says Plant Manager Timo Seppä from the Alavus water utility.
“The Tuuri area has grown rapidly over the last ten years and continues to grow. We decided to install two 100-cubic-metre low water tanks in the area to balance consumption peaks and help in preparing for potential failures.”
Ready from the factory
Before making the decision to purchase the reservoir tanks, the water utility studied other options. These included, for example, increasing the size of the supply lines, but soon it was clear that storing the water was the way to go. Seppä had cost estimates calculated for both concrete and plastic tanks.
Both the tanks and the pressure boosting station were made from Weholite polyethylene pipe with an inner diameter of 2.4 metres. The length of each tank is 23.4 metres.
Straight into the trench
GF delivered the products to the site in Tuuri in September 2020. The Alavus water utility had commissioned the necessary excavation work and the construction of foundations, on which the tanks and the pressure boosting station were lifted and anchored by GF’s installation team. After the anchoring was completed, the water utility connected the tanks to the pressure boosting station and water supply network and filled the trench. Now the only things that are visible above ground are three manhole covers and two control cabinets for the electrical and automation systems.
Installation was quick and smooth. The inlet and outlet fittings were exactly where they were supposed to be, so it was easy for us to fit the pipes and valves between them.
During the winter, the water utility’s own team continued to install the electrical and automation systems, and a decision was made to postpone commissioning so that it will take place closer to the summer, the high season of Tuuri. By that time, the installation of the remote monitoring of the tanks and the pressure boosting station will also be completed.